55 of 55 assignments
Status
| Project Name | Job # | Phase | Scheduled | Completion | Status | Notes | Actions |
|---|---|---|---|---|---|---|---|
| PJ-3011 | Startup | Oct 9, 2026 | Oct 17, 2026 | Scheduled | — | ||
| PJ-3006 | Equipment | Oct 2, 2026 | Oct 10, 2026 | Scheduled | — | ||
| PJ-3011 | Equipment | Sep 27, 2026 | Oct 5, 2026 | Scheduled | — | ||
| PJ-3003 | Startup | Sep 19, 2026 | Sep 27, 2026 | Scheduled | — | ||
| PJ-3018 | Startup | Sep 17, 2026 | Sep 25, 2026 | Scheduled | — | ||
| PJ-3013 | Equipment | Sep 9, 2026 | Sep 17, 2026 | Scheduled | — | ||
| PJ-3003 | Equipment | Sep 7, 2026 | Sep 15, 2026 | Scheduled | — | ||
| PJ-3005 | Startup | Aug 31, 2026 | Sep 8, 2026 | Scheduled | — | ||
| PJ-3005 | Equipment | Aug 19, 2026 | Aug 27, 2026 | Scheduled | — | ||
| PJ-3023 | Startup | Aug 19, 2026 | Aug 27, 2026 | Scheduled | — | ||
| PJ-3006 | Plumbing | Aug 15, 2026 | Aug 23, 2026 | Scheduled | — | ||
| PJ-3011 | Plumbing | Aug 10, 2026 | Aug 18, 2026 | Scheduled | — | ||
| PJ-3023 | Equipment | Aug 7, 2026 | Aug 15, 2026 | Scheduled | — | ||
| PJ-3016 | Equipment | Aug 5, 2026 | Aug 11, 2026 | Completed | — | ||
| PJ-3014 | Equipment | Aug 3, 2026 | Aug 11, 2026 | Scheduled | — | ||
| PJ-3026 | Startup | Jul 31, 2026 | Aug 6, 2026 | Completed | — | ||
| PJ-3025 | Plumbing | Jul 28, 2026 | Aug 5, 2026 | Scheduled | — | ||
| PJ-3007 | Plumbing | Jul 26, 2026 | Aug 3, 2026 | Scheduled | — | ||
| PJ-3013 | Plumbing | Jul 23, 2026 | Jul 31, 2026 | Scheduled | — | ||
| PJ-3003 | Plumbing | Jul 21, 2026 | Jul 29, 2026 | Scheduled | — | ||
| PJ-3027 | Startup | Jul 21, 2026 | Jul 29, 2026 | Scheduled | — | ||
| PJ-3018 | Plumbing | Jul 19, 2026 | Jul 27, 2026 | Scheduled | — | ||
| PJ-3026 | Equipment | Jul 19, 2026 | Jul 25, 2026 | Completed | — | ||
| PJ-3015 | Startup | Jul 16, 2026 | Jul 24, 2026 | Scheduled | — | ||
| PJ-3021 | Startup | Jul 16, 2026 | Jul 24, 2026 | Scheduled | — | ||
| PJ-3028 | Equipment | Jul 14, 2026 | Jul 22, 2026 | Scheduled | — | ||
| PJ-3027 | Equipment | Jul 9, 2026 | Jul 17, 2026 | Scheduled | — | ||
| PJ-3021 | Equipment | Jul 4, 2026 | Jul 12, 2026 | Scheduled | — | ||
| PJ-3005 | Plumbing | Jul 2, 2026 | Jul 10, 2026 | Scheduled | Confirm site access morning of. | ||
| PJ-3022 | Plumbing | Jun 28, 2026 | Jul 4, 2026 | Completed | — | ||
| PJ-3020 | Startup | Jun 26, 2026 | Jul 4, 2026 | In Progress | — | ||
| PJ-3008 | Plumbing | Jun 24, 2026 | Jun 30, 2026 | Completed | — | ||
| PJ-3023 | Plumbing | Jun 20, 2026 | Jun 28, 2026 | Scheduled | — | ||
| PJ-3002 | Equipment | Jun 19, 2026 | Jun 27, 2026 | In Progress | — | ||
| PJ-3016 | Plumbing | Jun 18, 2026 | Jun 24, 2026 | Completed | — | ||
| PJ-3014 | Plumbing | Jun 16, 2026 | Jun 22, 2026 | Completed | — | ||
| PJ-3009 | Plumbing | Jun 11, 2026 | Jun 19, 2026 | In Progress | — | ||
| PJ-3024 | Startup | Jun 11, 2026 | Jun 19, 2026 | Scheduled | — | ||
| PJ-3001 | Plumbing | Jun 8, 2026 | Jun 14, 2026 | Completed | — | ||
| PJ-3017 | Plumbing | Jun 6, 2026 | Jun 12, 2026 | Completed | — | ||
| PJ-3010 | Plumbing | Jun 1, 2026 | Jun 9, 2026 | In Progress | — | ||
| PJ-3026 | Plumbing | Jun 1, 2026 | Jun 7, 2026 | Completed | — | ||
| PJ-3012 | Startup | May 27, 2026 | Jun 4, 2026 | Scheduled | — | ||
| PJ-3028 | Plumbing | May 27, 2026 | Jun 4, 2026 | Scheduled | — | ||
| PJ-3027 | Plumbing | May 22, 2026 | May 30, 2026 | In Progress | — | ||
| PJ-3015 | Plumbing | May 17, 2026 | — | Delayed | Confirm site access morning of. | ||
| PJ-3021 | Plumbing | May 17, 2026 | May 23, 2026 | Completed | — | ||
| PJ-3012 | Equipment | May 15, 2026 | May 23, 2026 | Scheduled | Confirm site access morning of. | ||
| PJ-3002 | Plumbing | May 2, 2026 | May 8, 2026 | Completed | — | ||
| PJ-3020 | Plumbing | Apr 27, 2026 | May 3, 2026 | Completed | — | ||
| PJ-3019 | Equipment | Apr 25, 2026 | May 3, 2026 | In Progress | — | ||
| PJ-3004 | Plumbing | Apr 15, 2026 | Apr 21, 2026 | Completed | — | ||
| PJ-3024 | Plumbing | Apr 12, 2026 | Apr 18, 2026 | Completed | — | ||
| PJ-3012 | Plumbing | Mar 28, 2026 | Apr 3, 2026 | Completed | — | ||
| PJ-3019 | Plumbing | Mar 8, 2026 | Mar 14, 2026 | Completed | — |