Construction · Project Detail

Hiawassee CC — Tournament Pool Reno

Construction/Projects/Hiawassee CC — Tournament Pool Reno

Hiawassee CC — Tournament Pool Reno

In ProgressAt Risk
Job Number
PJ-3021
Address
1 Club Dr
Project Type
Pool Renovation
Salesperson
Devon Klein
Status
In Progress
Contract Amount
$218,900
Start Date
Apr 23, 2026
Target Completion
Jul 30, 2026(38d)
Last saved Apr 23, 2026 by Marcus Hale

Construction Readiness

Ready for ConstructionSigned ContractPermit IssuedEngineering Plans ApprovedCustomer Selections FinalizedDeposit / Financing Received

Pool Specifications

Freeform
16' x 32'
512 sq ft
3.5'
6.0'
Curved tanning ledge on east side, 8' x 4'.

Equipment Selections

Pentair IntelliFlo VSF
Pentair Clean & Clear Plus 520
Raypak 264k BTU Natural Gas
Jandy iAquaLink
Pentair IntelliChlor IC40 salt cell.

Finish & Material Selections

6" glass mosaic — Ocean Blue (National Pool Tile)
Pebble Sheen — Aqua Blue
Travertine pavers
Ivory — tumbled finish
880 sq ft
Travertine bullnose — Ivory

Features & Upgrades

Sheer descent waterfall (3), deck bubblers (2).
Stacked stone fire bowl (2).
None
ColorLogic 320 underwater (3), landscape path lighting (12).
Aluminum 4' pool fence — black, 180 LF.
None

Permits & Plans

Issued
BP-2026-04812
Apr 23, 2026
Approved
Soils report on file; rebar schedule per Engineer Stamp 04/2026.
Internal only — never appears on customer-facing documents.

Construction Notes

Site access via north driveway only. Verify spoils placement with homeowner before dig. Equipment pad set 18" off east wall.
Last edited by Marcus Hale · Apr 23, 2026

Build Instructions

Plumb 2.5" returns for waterfall. Pre-wire automation conduit during steel. Confirm tile pattern with customer before set.
Last edited by Marcus Hale · Apr 23, 2026

Scope Revision Notes

Addendum #1 — Added deck bubblers (2). Addendum #2 — Upgraded heater to 264k BTU.
Last edited by Marcus Hale · Apr 23, 2026